The statutory processing period for a public service is different from the duration of a complete SGR project. The project also includes documents, translation, sampling, logistics, testing and any necessary corrections.
What affects the timetable
Relevant factors include manufacturer-document readiness, the number of products and variants, laboratory availability, the testing programme, sample delivery and labelling quality. These differ between categories, so one deadline for every product is misleading.
Authority processing
Paragraph 16 of the Rules under Decision No. 80 sets a general maximum of 30 calendar days from receipt of the prescribed complete package, unless the technical regulation provides otherwise. For applications in Kazakhstan, check the current public-service rules and how the period is calculated. This period is not the time from first contacting a consultant to receiving the certificate.
Planning supply
Agree the evidence and tests first, then obtain a timetable identifying assumptions and dependencies. Clarify the applicant's, laboratory's and consultant's responsibilities. Changes in composition or incomplete information may require a revised estimate. ALMA TEST supports agreed stages and progress tracking but cannot guarantee that every participant will avoid delays or that the authority will approve the application.
Official sources
Reviewed against official sources on 11 November 2026. Publisher: ALMA TEST. Applicability is assessed using the particular product documentation.